The 2005-06 summer saw the completion and conditional occupancy signoff for the last three wings of the elevated station...among other things. So we'll start with a look at the newest berthing wing... |
The winter finish work continued into the early summer--like the carpet. |
Lots o carpet tiles! |
The air handler was cranking out heat. |
A bit later, the floor was prepped. The floor opening is the relief outside air intake. |
The DDC wiring hanging from the wall at left is waiting for the new panel enclosure to replace the one that was damaged in shipment. |
The corridor wall panels were installed... |
...as were the color tiles at the entrances, followed by the electrical panel covers. |
Flooring and finish trim in the first level vestibule. |
Early in the summer a subcontractor showed up to pull and terminate all the phone and data wiring. This is the first level of A3 looking west, the comms room is the first door on the left. |
All the orange fiber optic cable dangling from the ceiling in the left photo was terminated a day later. |
Those fancy funky window shades were installed. Why were they not blackout shades? Long long story...there had been plans for separate blackout shades but they were cancelled supposedly due to cost. |
A bit later on, the exterior stairwell was put together and installed (Rechelle Parent). |
And here it is complete. (Ki Won Yoon). |
Jump ahead a bit...after all was said, done, and accepted, A4 was used to store the potables. Here's some of the liquor and soda stacked in the first level womens'
room (Neal Scheibe). |
More of the quality beer in one of the completed and furnished berthing rooms (Neal Scheibe). |
Well, it seems that didn't work out too well; there were some heating problems and some of the stuff froze (Denis Barkats). |
Here's what the damage looked like before the cleanup (Denis Barkats). |
Hey, there's root beer in my network connection... (Denis Barkats)! The uncredited photos on this page are mine. |