Next, some framing, electrical and mechanical work. Here, the hallway (I). |
The carpenter shop (I). |
Looking from the main bay towards the UT shop (I). |
From about the same spot as the photo at left (but a bit earlier in the winter), here is the 1999 winter construction crew (!) (JM). |
The garage ceiling, with the painted crane rails (I). |
Did I mention that all of the floor plates needed to be welded, along with the drain trenches (I)? |
Thus...(I) |
Meanwhile, as things finished up on the building and ramps, the bulkhead was installed. This photo was taken in August (!) (I). |
The side deck work was also underway in August (I). |
Decking installation and framing of the firewall in one of the two connecting tunnels to the old garage/LO arch (FCA). |
Looking the other way towards the garage through the completed doorway (FCA). |
here's some of the cladding going on the low roof. I'm not sure when this was taken, but from what he's wearing I guess it is summer (NSF). |
A summer look at the downwind bulkhead (NSF). |
Here's the main bay of the garage getting its final touches (NSF). |
Again, conditional occupancy was achieved in December 1999 (!) Photo credits--well, I really don't have specific photographer credits for many of them. The one labeled JM is from Joel Michalski; those labeled (C) came from a presentation by Carlton Walker; those labeled (I) were found on the common drive; those labeled (FCA) from Ferraro Choi & Associates; those labeled (NSF) were credited accordingly. Some of these photos were provided with help by Brian Shunamon.
|